Alpha Generation, known as AlphaGen, an entity within ArcLight Capital Partners, is set to revamp its power generation capabilities significantly across New Jersey, Maryland, and Ohio. These upgrades, totaling nearly 450 megawatts (MW), are part of a wider strategy to improve grid reliability and respond to competitive market demands.

Overview of the Upgrades


The new enhancements will involve substantial capacity increases at several facilities:
  • - Linden Facility, New Jersey will see an addition of 309 MW.
  • - Bergen Generating Station, New Jersey will receive a 53 MW boost.
  • - Keys Energy Center, Maryland will enhance its output by 56 MW.
  • - Lordstown Energy Center, Ohio will achieve a 30 MW increase.

This move is anticipated to benefit roughly 450,000 households, providing a more reliable electricity supply amid fluctuating market conditions.

PJM's Endorsement


These projects were encouraged and fast-tracked by PJM, the regional grid operator responsible for monitoring and improving the reliability of the electricity grid. Their support underlines the importance of high-reliability projects aimed at enhancing power distribution efficiency. According to Curt Morgan, AlphaGen's CEO, the projects reflect a proactive response to clear market signals demanding increased generation capacity and the expectation of affirmative state support throughout the permitting processes.

Technical Enhancements


Bergen Project


The Bergen project promises significant enhancements through advanced upgrades to its gas turbines and steam turbine. These improvements will lead to increased operational efficiency and additional output, with completion projected for as early as 2027.

Linden Project


At the Linden site, a proposed upgrade to the steam turbines along with full upgrades to the combustion turbines aims to enhance overall efficiency while adding approximately 309 MW of capacity. This project is expected to commence by 2029-2030, reinforcing AlphaGen's commitment to sustainable energy solutions.

Keys and Lordstown Projects


The upgrades planned for the Keys and Lordstown facilities include advanced turbine efficiency packages designed to boost output while enhancing emission control and overall efficiency. Completion of these upgrades is projected for 2027, aligning with the increasing demand for sustainable energy solutions.

Context of the Upgrades


These expansions are particularly pertinent as local policymakers push to reduce dependence on external energy sources amidst rising demand. Unlike greenfield projects, which involve challenges related to site selection and environmental regulations, AlphaGen’s plans leverage existing infrastructure, minimizing delays often associated with new projects.

As Morgan stated, “AlphaGen is committed to optimizing existing resources to ensure consumers enjoy increased access to reliable power.” He also recognized the excitement surrounding potential future projects, dependent on the positive market climate maintained by PJM.

About AlphaGen


AlphaGen has emerged as a strategic partner within ArcLight Capital, focusing on owning and operating pivotal power infrastructures that meet the escalating demands for reliable electricity. With a substantial portfolio exceeding 11,000 MW of power operations spanning four Regional Transmission Organizations (RTOs), AlphaGen plays a crucial role in supporting energy reliability on a national scale. More information is accessible at www.alphagen.com.

About ArcLight Capital


Established in 2001, ArcLight is a national leader in infrastructure investment, managing extensive electrification projects and maintaining a vast network of energy assets valued at around $80 billion. Their operational approach emphasizes strategic investment across renewable energy sectors, enhancing reliability, security, and sustainability within the power market.

For press inquiries, media contacts are available through AlphaGen and ArcLight representatives, emphasizing their commitment to transparency and community engagement during these pivotal upgrades.

Topics Energy)

【About Using Articles】

You can freely use the title and article content by linking to the page where the article is posted.
※ Images cannot be used.

【About Links】

Links are free to use.