Silvercorp Metals Inc. Unveils Ambitious Plans for El Domo Project Development

Silvercorp Metals Inc. Unveils Ambitious Plans for El Domo Project Development



Silvercorp Metals Inc. has officially announced its detailed construction plan for the El Domo Project, indicating a robust vision for development set to bring significant changes to the region. The company is projecting an overall budget of $240.5 million for this venture, aligning closely with earlier feasibility study estimates. Set to bring the project into production by late 2026, Silvercorp is prepared to put extensive resources into optimally developing the site.

The company has been advancing engineering efforts since the initial feasibility study concluded in 2021, aimed at streamlining operations and constructing sustainable infrastructure. Furthermore, significant focus has been placed on comprehensive project management that reflects environmental considerations while aiming for efficiency.

Project Components


Silvercorp's strategy involves several key components:
  • - Advanced Engineering: Collaborative works with Klohn Crippen Berger (KCB) to design critical elements like the Tailings Storage Facilities (TSF) and implement optimized open-pit mining designs. Special attention is also devoted to integrating mining schedules with ongoing construction activities to ensure a smooth workflow.

  • - Infrastructure Development: A new public bypass road and operational haul roads are being designed to enhance site accessibility. The company has also executed a powerline contract with state-owned CNEL EP and is in the bidding phase for selecting contractors. Additionally, they are preparing for any power supply shortfalls in Ecuador by sourcing standby diesel generators.

  • - Construction Material Management: Silvercorp is organizing its construction tasks into various packages to keep operations streamlined. Bid packages include site preparation, open-pit mining, and the construction of essential site infrastructures such as a process plant and camps.

Financial Breakdown


The financial allocations for the project highlight meticulous planning:
1. Package #1 involves site preparation, including roads and channels, with costs estimated at $47.5 million.
2. Package #2, which focuses on open-pit mining and stripping, anticipates costs of $39 million.
3. Package #3, relating to the processing plant construction, is projected at $33 million.
4. Additional packages covering site infrastructure like bypass roads and power lines will also involve considerable investment.

Overall, direct costs alone have been lowered to $159.5 million, attributed largely to the implementation of unit cost contracts and reinforced engineering processes.

The clear strategy demonstrated by Silvercorp lays a promising foundation for the El Domo Project. Balanced by risk management and proactive planning, the company appears poised to capitalize on its ample growth prospects within the mining sector. As the landscape continues to evolve, Silvercorp's focus on generating robust shareholder value reflects a commitment to sustainable practices within the mining industry.

In closing, Silvercorp Metals Inc.'s commitment to the El Domo Project signifies not just a substantial investment in mining but also highlights a thoughtful approach towards addressing environmental and logistical challenges in Ecuador's mining landscape. Interested stakeholders are encouraged to monitor developments closely as site preparations begin, marking an important milestone in Silvercorp's journey to excellence in the mining field.