Entergy Texas Strengthens Power Grid with Major STEP Ahead Initiatives for Growing Communities

Entergy Texas Enhances Power Grid for Southeast Texas Growth



As Southeast Texas continues to flourish, Entergy Texas is proactively investing in the enhancement of its power grid through a strategic initiative known as the Southeast Texas Energy Plan, or STEP Ahead. The objective is straightforward — to ensure a robust and dependable energy infrastructure that can cater to the increasing power demands of the region, while also keeping customer rates reasonable.

Recent Developments


On December 12, 2025, the Public Utility Commission of Texas (PUCT) granted approval for the Cypress to Legend 500-kV transmission line, a project that spans approximately 41 miles through the counties of Hardin and Jefferson. This significant development completes the major project approvals planned for this year, rounding off a year dedicated to bolstering the energy framework of the area.

This approval follows the recent greenlighting of the Southline-Jacinto transmission line, underlining Entergy Texas' commitment to not only meeting but anticipating the growing energy needs of local communities. According to CEO Eliecer Viamontes, these enhancements are crucial for positioning Southeast Texas favorably for future growth while supporting job creation.

Key Projects Under STEP Ahead


The STEP Ahead plan encompasses several major projects aimed at strengthening the grid's reliability and resilience. These include:
  • - Texas Future Ready Resiliency Plan (Phase I): A $137 million initiative designed to fortify the grid against extreme weather events, thus reducing the expenses associated with storm restoration and minimizing outages over time.
  • - New Power Generation Resources: The plan includes the addition of new, 24/7 dispatchable power generation resources at facilities like the Legend and Lone Star power stations, which are vital for supporting the rising energy demands and simultaneously providing thousands of construction jobs in the region.
  • - SETEX 500-kV Transmission Line: This project improves the efficiency of power routing to rapidly expanding communities across Southeast Texas, enhancing overall grid reliability.
  • - Texas Energy Fund Grant: With $200 million allocated from state funds, this grant is aimed at amplifying grid resilience and reliability without imposing additional fees on customers.
  • - Legend-Sandling and Southline-Jacinto Transmission Lines: These lines are crucial in facilitating industrial growth and catering to the daily electricity needs of a growing populace as more families and businesses move into the area.

The Road Ahead


Moving into 2026, Entergy Texas is set to break ground on these initiatives, continuing its commitment to provide affordable, reliable, and sustainable energy solutions. The company recognizes the importance of long-term planning and strategic investments, paired with fruitful collaborations with state and local partners.

By focusing on these areas, Entergy Texas aims to stay a STEP Ahead, ensuring that it can meet the both current and future energy needs of Southeast Texas. To stay updated on the progress of the STEP Ahead initiatives, you can visit EntergyTexasStepAhead.com.

About Entergy Texas


Entergy Texas, a subsidiary of Entergy Corporation, brings electricity to over 524,000 customers across 27 counties. With a commitment to improved reliability and enhanced energy solutions, Entergy Texas plays a significant role in powering life for approximately 3 million customers across its operating regions. The company is also committed to sustainability, investing in cleaner energy sources such as modern natural gas, nuclear, and renewable energy technologies. Recognized as a leader in corporate responsibility, Entergy provides considerable economic benefits to its communities through philanthropic efforts and community support. For further details, visit EntergyTexas.com.